June 12 14, 2006 LGS Engineering Run Pre run engineering work 6/5 6/6 BTO work schedule laser sched 060606.pdf: CSFL tasks for 6/06 LGS engineering run...
LGS Team Meetings Team meetings are held once per month, on 3:30pm 5:00pm on Thursdays in 023 Robinson on the Caltech campus. A video conference system is available...
PALM LGS High Order Wavefront Sensor AWFS Dynamic Aperture.doc: Two page summary of the Dynamic Aperture Device (Trash.Palomar PalmLGSDAD) RichardDekany...
January 5 7, 2007 LGS engineering run Safety documents Cleared by FAA for laser projection 18:00 05:45 PST. Spotters scheduled to be on site 20:00 06:...
December 6 8, 2006 LGS engineering run Schedules and calendars Dec. engineering run personnel schedule (v3) A. Bouchez 12/05/06 (v2) Safety documents...
August 2006 Laser Move from Coude to AO lab Laser move preparations Pictures taken at Palomar by VNV: JPG: ID of connector 0.155` (may need to be reamed...
October 11 13, 2006 LGS Engineering Run Project schedules and task lists task schedule, v1 A. Bouchez 10/2/06 Oct. engineering run personnel schedule...
Cabling and Data Transfer by Anna Moore and John Henning The following summarises the current cabling installed on the 200inch telescope. We describe how signals from...
Solidworks Models of the LLT bench by Anna Moore and Hal Petrie Externally supplied SW part models of components Newport U100 A2K NL.SLDPRT: Newport 1` kinematic...
PALAO bench subsystem The PALAO bench is placed onto the 200` Hale telescope at the Cassegrain focus and contains (1) the science instrument; (2) the adaptive optics...
LGS AO Library LGS AO system characterization Dam et al. 2006, The W.M. Keck Observatory laser guide star adaptive optics system: Performance characterization...
Spie2006 Orlando, 24 31 May 2006 Presentations and posters spie06 palomarlgs.pdf: Bouchez et al., Laser Guide Star Adaptive Optics at Palomar Observatory,...
05/16/06 Experiments and Analysis Conclusions I suggest replacing the M2 mirror with an enhanced aluminum version, such as CVI part EAV PM 4050 C ($730). This will...
All, I just returned from a long day at Palomar. Here`s what I got done on the BtO: (I will also post this on the TWiki site BtO page...) 1. Checked stability and...
CSFL upgrade purchase list: 1. Coarse Filter parts : a. Filter enclosure : Mc Master CArr # 6882K1 Bttm Load Hi Purity Single Cartridge Housing for 9 3/4 To...
Vendor list Non linear Crystal databaseDocument Actions last edited 3 months ago by abouchez Conex systems, Inc. San Ramon, CA Ph: 925 735 8825 Contact Ting...
Astronomical Telescopes and Instrumentation 2006 Advances in adaptive optics CSFL spie.pdf: preprint of paper on LGS testbed at Palomar observatory ViswaVelur...
August 17 20, 2005 NGS Engineering Run Test schedule: 050818 engplan v2.pdf: NGS Engineering schedule v2 Test plans: Night logs: AntoninBouchez 13 May 2006
September 19 22, 2005 LGS Engineering Run Test schedule: 050920 engplan v2.pdf: LGS engineering test schedule v2 Test plans: Night logs: palm lgs log...
February 9 11, 2006 NGS Engineering Run Test schedule: lgs0602 schedule v2.xls: Engineering test schedule, v2.1 Test plans: testplan 0602 lowfs perf.pdf: LOWFS...
January 11 12, 2006 NGS Engineering Run Test schedule: lgs0601 schedule v4.xls: LGS Engineering test plan v4 Test plans: Night logs: AntoninBouchez 12 May...
November 14 18, 2005 LGS Engineering Run Test schedule: lgs0511 schedule v2.xls: LGS Engineering schedule v2 Test plans: Night logs: palm lgs log 051116.txt...
April 13 15, 2006 LGS Engineering Run Test schedule: lgs0604 schedule v3.xls: lgs0604 schedule v3.xls Test plans: Night logs: https://www.oir.caltech.edu...