August 11-13, 2007 LGS observing run
Night logs and results
8/11/08 UT
Aligned BTO, laser. Laser power 7.5-7.2 W. Canceled LGS operations at 10pm due to lack of FAA approval for projection. Performed NGS engineering/science remainder of night.
Safety Documents
- Laser projection schedule:
- 20:36:00 8/11/08 - 05:10:00 8/12/08 PDT
- 20:34:00 8/12/08 - 05:11:00 8/13/08 PDT
- 20:33:00 8/13/08 - 05:12:00 6/17/08 PDT
- Securitas spotters are schedule to be on site 18:30 - 5:15 PDT on 8/11, 19:30 - 05:15 PDT subsequent nights.
- US-STRATCOM documents:
Personnel and engineering schedules
|
Mon 8/11 |
Tue 8/12 |
Wed 8/13 |
Bouchez |
X |
X |
X |
Cromer |
X |
X |
X |
Dekany |
|
|
X |
Kibblewhite |
X |
|
|
Roberts |
X |
X |
|
Velur |
X |
X |
|
Kajsa |
X |
X |
X |
Note: SURF students are visiting 3:00pm-10:00pm on Wed. 8/13.
Target lists and finding charts
Engineering Schedule and Test Plans
Please post your test plans on the
Test Plan Library page, and add a link below.
- AO setup
- AO system internal focus: doc, pdf
- AO bench setup and checkout: doc, pdf
- BTO setup
- BTO setup (v2.4): doc, pdf
- BTO alignment (v2.4): doc, pdf
- BTO alignment, abbreviated version (v1.0): doc, pdf
- BTO shutdown (v1.1): doc, pdf
- Observing procedures:
- NGS Checkout (v3.1): doc, pdf
- LGS Checkout (v1.0): doc, pdf
- LGS target acquisition (v4.0): doc, pdf
- Engineering experiments:
- AO Optimization on the laser at zenith: doc, pdf
- Low-order loop optimization: doc, pdf