Oct. 9, 2009 UT LCROSS Impact Imaging
Contact Information
Schedule (Times UT, updated 10/6/09)
- ~02:00 Spacecraft separation
- 08:30 Acquire moon; determine best feature to use for AO lock
- 10:30 Begin impact imaging sequence
- 11:31:19 Centaur impact
- 11:35:45 Shepherding spacecraft impact
- 12:00 End impact imaging sequence
- 14:00 NASA ARC press conference (submit graphics by 12:30)
Finder Charts
Ephemeris, Timelines, Etc.
Links