Palomar LGS Project Planning
FY 2006
Preparations done to move the laser downstairs (07/27/2006 --- Pictures taken at Palomar) - VNV
Pictures and description
- DCP_2753.JPG: ID of connector = 0.155" (may need to be reamed)
- DCP_2755.JPG: long cable with collars and connectors - only one set (powers one IR laser completely) has been made to 10 m length. Need to agree on performance before brazing (w/ silver solder) the other 2 sets.
- DCP_2756.JPG: whole cable
- DCP_2757.JPG: shows a flat cable that has not been brazed
- DCP_2759.JPG: OD of the connector = 0.390"
- DCP_2761.JPG: OD of the connector with heat shrink insulation on top of connector = 0.438"
- DCP_2762.JPG: Modelocker electronics, TV monitor, spectrum analyzer electronics -- needed to be moved here so the laser can be moved out of the laser room
- DCP_2763.JPG: O'scope, IR viewer, vaccum/ positive pr. apparatus etc. at the bottom end of the Coude.
- DCP_2767.JPG: Chiller unplugged and ready to be moved -- the small chiller has its hoses still connected in closed circuit as we will use the "new" small chiller downstairs.
- DCP_2768.JPG: another view of previous pic.
- DCP_2769.JPG: Table cleaned up, all cables have been unplugged from the rack on the top step.
- DCP_2770.JPG: laser ready to be transported
- DCP_2771.JPG: laser ready to be transported
- DCP_2772.JPG: laser lab (downstairs) has been cleaned. Merle Sweet is on the picture as well. He approved that he can move the laser with the work done.