September 18-21, 2007 LGS observing run
Night logs and results
Safety documents
- FAA approved laser projection times:
- 19:45:00 9/18/07 - 05:38:00 9/19/07 PDT
- 19:44:00 9/19/07 - 05:39:00 9/20/07 PDT
- 19:42:00 9/20/07 - 05:40:00 9/21/07 PDT
- 19:41:00 9/21/07 - 05:40:00 9/22/07 PDT
- Securitas spotters are schedule to be on site 19:00 - 05:45 PDT.
- US-STRATCOM documents:
Personnel and engineering schedules
|
Tue 9/18 |
Wed 9/19 |
Thu 9/20 |
Fri 9/21 |
Angione |
X |
|
|
|
Bouchez |
X |
|
X |
X |
Cromer |
X |
X |
X |
X |
Roberts |
X |
|
X |
X |
Tripathi |
X |
|
X |
X |
Procedures and test plans
Please post your test plans on the
Test Plan Library page, and add a link below.
- AO setup
- AO system internal focus: doc, pdf
- AO bench setup and checkout: doc, pdf
- BTO setup
- BTO setup (v2.4): doc, pdf
- BTO alignment (v2.4): doc, pdf
- BTO alignment, abbreviated version (v1.0): doc, pdf
- BTO shutdown (v1.1): doc, pdf
- Observing procedures:
- NGS Checkout (v3.1): doc, pdf
- LGS Checkout (v1.0): doc, pdf
- LGS target acquisition (v4.0): doc, pdf
- Engineering experiments:
- AO Optimization on the laser at zenith: doc, pdf
- Low-order loop optimization: doc, pdf
This topic: Palomar/PalmLGS
> Eng_070918
Topic revision: r7 - 2007-09-21 - AntoninBouchez