August 23-25, 2007 LGS observing run
Safety documents
- FAA approved laser projection times:
- 20:22:00 8/23/07 - 05:18:00 8/24/07 PDT
- 20:21:00 8/24/07 - 05:19:00 8/25/07 PDT
- 20:19:00 8/25/07 - 05:20:00 8/26/07 PDT
- Securitas spotters are schedule to be on site 19:30 - 05:30 PDT.
- US-STRATCOM documents:
Personnel and engineering schedules
|
Thu. 8/23 |
Fri. 8/24 |
Sat. 8/25 |
Angione |
X |
X |
? |
Bouchez |
X |
X |
X |
Cromer |
X |
X |
X |
Fogarty |
X |
X |
|
Guiwits |
X |
|
|
Petrie |
X |
|
|
Roberts |
X |
X |
X |
Tripathi |
X |
X |
X |
Trinh |
|
X |
|
Engineering Schedule
Procedures and test plans
Please post your test plans on the
Test Plan Library page, and add a link below.
- AO setup
- AO system internal focus: doc, pdf
- AO bench setup and checkout: doc, pdf
- BTO setup
- BTO setup (v2.3): doc, pdf
- BTO checkout: doc (v2.3), pdf (v2.3)
- BTO shutdown (v1.1): doc, pdf
- Observing procedures:
- NGS Checkout (v3.1): doc, pdf
- Laser Acquisition (v5.1): doc, pdf
- LGS target acquisition (v4.0): doc, pdf
- Engineering experiments:
- AO Optimization on the laser at zenith: doc, pdf
- Low-order loop optimization: doc, pdf
Night logs and results