PTF project plan (UNDER CONSTRUCTION)

TaskSorted ascending Subtask Subsubtask Timeframe Lead
5-day cadence       Eran
Before first light     Mid-Sep 08 Nick
Design review       Arne
Dynamic cadence       Mansi
First light tests     End-Sep 08 Nick
First science night     Mid-Oct 08  
Initial science run
Instrument (summary)
  Pick target fields      
  Pick target fields      
  Get current pointing performance      
  Decide a plan to match requirements      
  Camera mounting to telescope      
  Software control of camera on telescope      
  Scheduler control of telescope      
  Astronomical photons -> camera?      
  Shutter operation      
  Filter change operation      
  Taking & storage of science images      
  Image quality      
  Throughput      
On-sky tests
Pointing       Nick
Scheduler       Eran
Scheduling       Eran
Science preparation
Telescope preparation

Edit | Attach | Watch | Print version | History: r3 < r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r2 - 2007-11-20 - NicholasLaw
 
  • Edit
  • Attach
This site is powered by the TWiki collaboration platform Powered by PerlCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback