Commissioning Activities
Engineering (Sept 6 - Oct 2, 2017)
Added:
>
>
Cryostat Arrival
Trim Plate Arrival
First Light
Flatfield Illuminator Arrival
Filter Exchanger Arrival
Science capability (Oct 2 - Dec 31, 2017)
astrometric test: follow field through the night and look at astrometric residuals as a function of airmass
Added:
>
>
I-band Filter Arrival
\ No newline at end of file