---++MOVE FROM CAHILL TO PHYSICS BUILDING HIGH BAY (SYNCOTRON) * Peter and Charlie moved all hardware to the cold box located in Syncotron * Test Cube w/ stages (no module installed, no camera installed) was moved by Peter, Hector and (forgot name) on Wednesday, January 14th * Verified that Andor camera is in proper focus and centered with all fibers in FOV (26 Cobra fibers + 5 fiducial fibers) * Everything is wired up and ready for the JPL drive electronics to be cabled up to the master board and new software (Virtex & mSim) to be updated (planned for Tuesday, 1/20) -- Main.CharlieFisher - 16 Jan 2015