Through a series of observing runs, characterize the instrument and develop and test the automated operation.

Current Major Items:

  • Re-acquire pointing model data once secondary stabilized (should be done with SEDM RC)
  • Instrument Throughput: characterize both spectroscopic and photometric throughputs (Don, Nadia)
    • throughput now characterized with Standard stars.
  • Operational Efficiency: characterize procedures that will optimize target observing (Don, Nadia, Richard)
    • pointing still limits acquisition and requires astrometry.net interaction. Consuming ~40s of overhead per science target.

Completed Items:

  • Fix secondary vacuum system to improve pointing stability (Oct 13-17, 2016)
  • Re-acquire pointing model data once secondary stabilized (Done with testing camera, Oct 13-17, 2016)
  • IFU optics stabilized by clamp that replaces spring
  • Calibration Lamps: now fully automated
  • DRP wavelengths: calibrated using Xe, Cd, and Hg arc observations
  • RC photometry: automated pipeline completed
  • Instrument Control: robotically operated
  • Data Reduction: photometry is completely automated, spectroscopy required minimal interaction

Commissioning Reports:

-- DonNeill - 19 Nov 2015

Topic attachments
I Attachment History Action Size Date Who Comment
Microsoft Word filedocx SEDMCommissioningReport01.docx r1 manage 155.9 K 2015-11-19 - 12:47 DonNeill SEDM Commissioning Report 01

This topic: Palomar/SEDM > WebHome > CommissioningPlans
Topic revision: r4 - 2016-10-17 - DonNeill
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback