<Keck NGAO Team Meeting #3>

9:50a - 2:30p PST
Wednesday, December 13, 2006
Tele/Videoconference

Dial-in Number: 977-280-4645 Passcode: 540030 Videoconference IP: 128.171.99.70 (Hualalai CR)


In effigie (e.g. on the phone): Adkins, Bauman, Flicker, Dekany, Gavel, Johannson, Le Mignant, Liu, Marchis, Max, Neyman, Velur, Wizinowich

Action Items from the meeting. Status of Action Items as of 2/28/07.

Goals:

  • Review Progress on Performance Budgets
  • Review Recent Trade Studies

Agenda:

  • 9:50 am Welcome
  • 10:00 am Management Report (Wizinowich) Management Report
    • Review study overall progress, progress against milestones, and summary financial situation
  • 10:25 am Science Team Report (Max) [Verbal Report]
  • 10:45 am Systems Engineering Report (Dekany) Systems Engineering Report (.ppt)
    • Review the status of all performance and efficiency budgets; identify areas needing additional science input.
  • 11:10 am Trade Study Report: MOAO & MCAO (Gavel) Report (pdf) supplement (ppt)
    • From the WBS Dictionary: This trade study is intended to build our expertise with Multi Object and Multi Conjugate AO. The existing MOAO and MCAO design studies should be reviewed. The product should be a summary of the issues related to these two approaches, including an understanding of the potential risks, technical challenges, limitations, advantages and room for improvement with each of these approaches.
  • 11:40 am Trade Study Report: Rayleigh Rejection Strategies (Velur) Rayleigh_rejection.ppt
    • From the WBS Dictionary: Evaluate the impact of unwanted Rayleigh backscatter to NGAO system performance. Consider the relative performance, cost, risk & schedule of various strategies for mitigation of LGS Rayleigh backscatter. Techniques include background subtraction, modulation & optimizing projection location. This issue is closely coupled to laser pulse format, with pulsed lasers generally providing more options for Rayleigh mitigation than CW lasers. Complete when NGAO baseline architecture selected.
  • 12:00 pm Trade Study Report: Stand-alone T/T vs. DM on T/T Stage (Bauman) tip-tilt_platform_design_study_presentation.ppt
    • From the WBS Dictionary: Consider the performance, cost, risk, reliability, and maintainability of a stand-alone tip/tilt mirror vs. mounting an otherwise necessary mirror (e.g. a DM) on a fast tip/tilt stage. Note that high BW correction is difficult with a large or heavy mirror. Complete when tip/tilt approach selected.
  • 12:20 pm Break
  • 12:40 pm Update on Instrument Trade Studies (Adkins)
    • Science Instrument Reuse Cost/Benefit. From the WBS Dictionary: Consider the cost/benefit of reuse of existing Keck AO instruments, particularly OSIRIS and NIRC2, versus the benefit of design freedom for an all-new instrument suite. Instrument-Reuse-NIRC2-121206.ppt
    • Instrument Balance. From the WBS Dictionary: Consider the relative merit of installing NGAO on Keck I vs Keck II. This must take into account the long-term instrumentation strategy for Keck, available laser infrastructure, and impact on operations. Complete when architecture and location requirements documented.
  • 1:00 pm Upcoming tasks and milestones (Wizinowich) .ppt
  • 1:20 pm Discussion: Issues pertaining to ongoing and upcoming work (All)
  • 2:30 pm Adjourn

Topic attachments
I Attachment History Action SizeSorted ascending Date Who Comment
Microsoft Word filedoc Meeting_3_Action_Items.doc r1 manage 30.0 K 2006-12-13 - 23:30 PeterWizinowich  
Microsoft Word filedoc Meeting_3_Action_Items_Status.doc r2 r1 manage 31.5 K 2007-02-28 - 21:37 PeterWizinowich Status of Meeting 3 action items (2/28/07)
PowerPointppt tip-tilt_platform_design_study_presentation.ppt r1 manage 38.5 K 2006-12-13 - 21:33 UnknownUser  
PowerPointppt Instrument-Reuse-NIRC2-121206.ppt r1 manage 80.5 K 2006-12-13 - 16:51 UnknownUser  
PowerPointppt MOAO_vs_MCAO.ppt r1 manage 128.5 K 2006-12-13 - 17:53 UnknownUser  
PowerPointppt NGAO_meeting_#3.ppt r2 r1 manage 161.5 K 2006-12-13 - 02:48 PeterWizinowich Management Report
PowerPointppt NGAO_meeting_3.ppt r1 manage 161.5 K 2006-12-13 - 03:30 PeterWizinowich Management Report
PDFpdf MOAOvsMCAODesignStudyReport_Draft1.pdf r2 r1 manage 371.0 K 2006-12-13 - 17:34 UnknownUser  
PowerPointppt Rayleigh_rejection.ppt r7 r6 r5 r4 r3 manage 881.5 K 2006-12-13 - 17:08 UnknownUser Rayleigh rejection Version 1.2
PowerPointppt NGAO_Sys_Eng_Status_061213.ppt r1 manage 1159.5 K 2006-12-13 - 08:12 RichardDekany  
Edit | Attach | Watch | Print version | History: r31 < r30 < r29 < r28 < r27 | Backlinks | Raw View | Raw edit | More topic actions
Topic revision: r31 - 2007-02-28 - PeterWizinowich
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback