May 18, 2008 NGS Engineering

Goals

Line: 14 to 14
 
      • Tune image on PHARO
    • Test iterative reconstructor with AO stimulus - L. Lessard
  • Nighttime tests
Added:
>
>
    • PHARO vignetting: In twilight, verify even illumination of PHARO wide field.
 

Revision 42008-05-18 - AntoninBouchez

Line: 1 to 1
 
META TOPICPARENT name="WebHome"

May 18, 2008 NGS Engineering

Goals

Line: 18 to 18
 
Added:
>
>
 

Revision 32008-05-13 - AntoninBouchez

Line: 1 to 1
 
META TOPICPARENT name="WebHome"

May 18, 2008 NGS Engineering

Goals

While basic checkout and calibration of the NGS-AO system were successfully accomplished on April 9, 2008, performance tests were not possible due to clouds and poor seeing. The primary goal of this additional NGS engineering night is to complete the performance characterization of the NGS-AO system after the winter 07/08 optical bench relayout. A secondary goal is the testing of a new iterative reconstructor by L. Lessard and D. MacMynowski.

Personnel schedule

Changed:
<
<
Planning to be present on 5/12/08 (local): Bouchez, Lessard, Roberts, MacMynowski.
>
>
Planning to be present on 5/18/08: Bouchez, Lessard, Roberts, MacMynowski.
 

Procedures and test plans

Please post your test plans on the Test Plan Library page, and add a link below.
Line: 16 to 16
 
Added:
>
>
 
Changed:
<
<
>
>
 

Revision 22008-05-12 - AntoninBouchez

Line: 1 to 1
 
META TOPICPARENT name="WebHome"

May 18, 2008 NGS Engineering

Goals

Changed:
<
<
While some basic checkout of the NGS-AO system was accomplished on April 9, 2008, performance tests were not possible due to clouds and poor seeing. The primary goal of this additional NGS engineering night is to complete the performance characterization of the NGS-AO system after the winter 07/08 optical bench relayout. A secondary goal is the testing of a new iterative reconstructor by L. Lessard and D. MacMynowski.
>
>
While basic checkout and calibration of the NGS-AO system were successfully accomplished on April 9, 2008, performance tests were not possible due to clouds and poor seeing. The primary goal of this additional NGS engineering night is to complete the performance characterization of the NGS-AO system after the winter 07/08 optical bench relayout. A secondary goal is the testing of a new iterative reconstructor by L. Lessard and D. MacMynowski.
 

Personnel schedule

Planning to be present on 5/12/08 (local): Bouchez, Lessard, Roberts, MacMynowski.

Revision 12008-05-12 - AntoninBouchez

Line: 1 to 1
Added:
>
>
META TOPICPARENT name="WebHome"

May 18, 2008 NGS Engineering

Goals

While some basic checkout of the NGS-AO system was accomplished on April 9, 2008, performance tests were not possible due to clouds and poor seeing. The primary goal of this additional NGS engineering night is to complete the performance characterization of the NGS-AO system after the winter 07/08 optical bench relayout. A secondary goal is the testing of a new iterative reconstructor by L. Lessard and D. MacMynowski.

Personnel schedule

Planning to be present on 5/12/08 (local): Bouchez, Lessard, Roberts, MacMynowski.

Procedures and test plans

Please post your test plans on the Test Plan Library page, and add a link below.

Results

 