April 9, 2008 NGS Engineering
Goals |
| Please post your test plans on the Test Plan Library page, and add a link below.
- Daytime tests
- AO bench setup and checkout (2 hrs) - J. Roberts
|
|
> > |
-
-
- Align PHARO focus and pupil (DM and telescope).
|
|
-
-
- Tune image on PHARO
- Check centration of field stop.
|
|
< < |
-
-
- Check AO to telescope pupil alignment.
- PHARO pupil motion (1 hr, telescope operator required) - A. Bouchez
- Stimulus/AO system flexure (1 hr, telescope operator required) - R. Burruss
- Demonstrate WL acquisition at all zenith angles.
- Test Plan
|
> > | |
|
- Nighttime tests
- SSM motion and pupil registration (1 hr) - J. Roberts.
- SSM range, pupil/image motion control, centroid to pupil motion gain)
|
|
-
-
- V=6?, 8, 10, 12, 14
- Test reconstructors?
- Predictive AO data (10-15 min per data collection, multiple times per night (3-4) if possible) - M. Troy.
|
|
< < | |
> > | |
|
-
- Throughput (1 hr; clear) - R. Burruss.
|
|
< < | |
> > | |
|
-
- Platescale (PHARO, ACAM, LOWFS) (1 hr) - A. Bouchez
|